$46,557,474
Drydock 4 and Pier 3 Modernization, Bremerton, WA
The scope at Drydock 4 also involved upgrading mechanical systems (i.e., fresh water) and electrical gear (i.e., shore/industrial power mounds) within the existing galleries within the drydock (6 each on the east side and 6 each on the west side). Additionally, the existing gallery structures (i.e., walls, stairs, floors) were demolished and then re-poured, upgrading them with more room.
Lastly, project scope also involved work on Pier 3. On Pier 3, two substations were modified/upgraded with new foundations, fencing, and gear. Existing shore/industrial power equipment was upgraded with new gear. Additionally, new structural hangers and an under-pier duct bank were installed under the pier. Hangers consisted of both stainless steel and fiberglass components. The conduit was fiberglass as well.
Completion:
2023