Projects

CLIENT:

US Navy

LOCATION:

Travis AFB, CA

VALUE:

$6,112,563

Repair Bulk Fuel Storage Tanks

This project repaired two 55,000-barrel bulk JP-8 fuel storage tanks. Repairs included one new 100-foot diameter concrete ringwall foundation that was 2 feet thick by 4 feet tall, as well as modifications to an existing ringwall foundation.

Other work included an FML liner system under the tank, impressed current cathodic protection system for the new steel floor bottom, modifications to the tank appurtenances, installation of tank level alarms, a new aluminum geodesic dome roof, and 700 linear feet of 12-inch carbon steel underground and aboveground piping. Nova removed and replaced the existing concrete containment basins. 

COMPLETION:

2004

Nova Group, Inc. is an equal opportunity employer. 

SITE MAP